“As we turned the corner from the West Jetty, piling operations have passed the 75% completed mark. Two further sections of jetty deck have been poured during this period and operations continue to progress from both the East and West jetties. Service installation is advancing with the works as we continue with precast beam installation and prepare to recommence piling operations from the East Jetty.
A ’Projects Open Day’ was hosted by SFPC during this period. With an impressive attendance from staff and stakeholders alike, we utilised this opportunity to showcase progress to date on what are valuable infrastructural developments for Foynes Port.”