“Several critical activities such as piling works and tie rod installation were completed during this period enabling us to progress the importation of fill material and commence preparation works for the installation of site services. To date, approximately 80% of required 6N infill material has been delivered to site. Some milestone activities planned for the next period include the installation and testing of the new molasses pipeline as well as the erection and commissioning of high mast lighting and site services.”