“Piling works are ongoing as we surpassed the 90% completed mark.Precast beams and deck slabs were placed as a further section of jetty deck was poured on the east side covering an area of approximately 480m2.During this period, we received delivery of fenders, lighting masts, toe rails and bollards – All of which form part of the furniture & fixture installation phase of the works as we near the completion stage of the project”