“Piling works continue as all 44no. tubular combi wall piles are now pitched. Infill works are advancing well as the excavation of silt material, placement of geotextile and the importation of fill material are all carried out in parallel. The main work elements programmed for the next period will involve the installation of the return sheet pile wall and the anchor return wall. Back of quay wall drainage works are also planned with the contractor working to maximise resources as works are programmed around tidal conditions.”