Exclamation Progress Update January 2023

“With only 9no. tubular combi wall piles left to be pitched, piling works have advanced well in the last period. The main anchor wall sheet piles have progressed past the 70% completed mark as the importation of stone infill continued. The main work element programmed for the next period involves the continuation of piling operations. We also plan to advance infill operations with the continued excavation of silt material, placement of geotextile and the importation of fill material.”

Reclamation Aerial View
Piling Operation
Combi Wall Piles
Pitching Piles No. 15 = 20
Anchor Wall Installation
Aerial Combi and Anchor Wall Piling