“We achieved an important project milestone during this period with the completion of piling works – the last of 89 piles was driven to set enabling the commencement of the last section of precast beam and deck plank installations. Works associated with the connection of water, drainage and electrical ducting services continued along with preparations for the installation of jetty fendering.”