Exclamation Progress update November 2022

“With the contractor firmly mobilised to site, establishing safe site access was a priority along with progressing with the placement of geotextile and the importation of fill material. Localised concrete demolition works have been undertaken to accommodate the successful removal of 4no. disused fender panels and their supporting box piles. Having received delivery of our 1829mm diameter tubular combi wall piles the main work elements programmed for the next period involves the kick off of piling operations as well as advancing the importation of stone infill.”

Access and Demolition Works
Fender Removal
Aerial of Infilling Works

Importation of Fill Material
Prep work to 1829mm Combi Wall Piles