“Contractor fully mobilised to site with compound established. Site specific traffic management in place controlling access & egress to the site. Pre commencement documentation was issued to all relevant parties and site clearance works have commenced. An archaeologist is on site monitoring progress and imported fill material from a licenced facilities is being placed and compacted in layers. The primary activities over the coming weeks are to continue importing fill material and to progress with preparations to construct proposed culvert crossings as well as works on extending the attenuation area.”